Can You Start Next Week? Check Consulting Capacity Before You Promise

A prospective client wants a start date before signing the proposal. Your team has space somewhere in the calendar, but the analyst who would do the work and the specialist who must review it are busy at different times. A quick “yes” can commit both people before either has agreed.

Before promising the date, make the proposed assignment visible alongside existing work. The decision is whether to accept this new commitment, offer a different sequence or decline it. An opportunity's expected revenue does not answer that scheduling question.

Turn the assignment into demand for specific people

Start with the proposed outputs and the sequence needed to produce them. Identify the skills required, the effort in each week and any work that depends on someone else's contribution. A five-day assignment may need two analyst days immediately, a specialist's review halfway through and three further analyst days afterwards.

Ask the people responsible to check those estimates. Include preparation, client meetings and the expected review effort. If the proposal depends on a client's access approval or an external specialist, record when that dependency must be confirmed.

The Association for Project Management includes skills, time commitments and dependencies in its resource capacity planning guidance. The worksheet below is a small-team application of those principles, with invented figures for illustration.

Use remaining availability rather than nominal working days

For each person, identify schedulable days after known absence. Then subtract existing delivery commitments and necessary internal work. If absence is already excluded from the starting figure, do not subtract it again.

Keep proposal work visible too. A consultant who has four unallocated days on a project plan may already owe a day to preparing bids and internal reviews. Record that work once, wherever your team plans it consistently.

Use a separate list for unconfirmed holds. Give each hold an owner, a reason and an expiry or decision date. That prevents a tentative discussion from silently becoming either a firm booking or apparently free time. Show the schedule with those holds as well as the firm commitments before allocating the same days to a new client.

For named people, check their own availability. Combining everyone's spare days into one team total will not show a shortage in the only role qualified to perform a particular task.

Work through a start-date conflict

In this fictional example, a consultancy is considering a process review. The client requests a Week 1 start. The analyst needs two days in Week 1, two in Week 2 and one in Week 3. A technical specialist must contribute half a day in each of the first two weeks. The first specialist session is required before the analyst can finish the opening phase.

All figures below are days. “Schedulable” already excludes absence. Internal work is reserved separately. There are no unconfirmed holds in this example.

Person and calculation Week 1 Week 2 Week 3 Week 4
Analyst: schedulable 4 4 4 4
Analyst: existing delivery 2 1 1 1
Analyst: internal and proposal work 1 1 1 1
Analyst: remaining availability 1 2 2 2
Specialist: schedulable 1 1 1 1
Specialist: existing delivery 1 0 0 0
Specialist: remaining availability 0 1 1 1

The requested start fails two checks. Week 1 needs two analyst days but has one available. It also needs half a specialist day but has none. Spare analyst time in Week 4 cannot resolve either shortage in Week 1.

The team tests a Week 2 start using the same sequence. Analyst demand becomes two days in Week 2, two in Week 3 and one in Week 4. Specialist demand becomes half a day in Week 2 and half a day in Week 3. Each demand now fits the corresponding person's available days.

The project lead then checks the order within those weeks: the specialist is available for the opening session before the dependent analyst work. The client confirms that its staff can attend the revised sessions. Both consultants agree to the allocation.

The resulting proposal offers a Week 2 start and a Week 4 completion, subject to the stated agreement deadline and client inputs. The team records those particular days as reserved until that deadline. It does not promise the original start date on the strength of an overall team total.

Choose among feasible alternatives

A later start is one option. A smaller opening phase may also work if it produces a useful output without the unavailable specialist. Check that revised scope and sequence rather than merely renaming the kickoff.

An external partner is another possibility when the required skills, actual availability, cost, client acceptance and handover are confirmed. “We can find someone” is still an unresolved dependency. If the client's deadline is fixed and no acceptable arrangement fits, decline that deadline or the assignment.

A sales probability can help explore possible future demand. It does not turn a two-day commitment into one day of actual work because the opportunity has a 50% chance of closing. Once accepted, the work needs its full allocation.

Copy this admission decision record

Keep the capacity sheet with a short decision that another colleague can understand:

Field What to record
Proposed assignment Outputs, estimated effort and required skills
Requested sequence Start, review points, completion and client dependencies
Capacity evidence Dated role-by-week sheet and the people who checked it
Unconfirmed holds Owner, competing demand and decision deadline
Chosen option Accept, revise date or scope, confirm partner, or decline
Conditions What must be confirmed before the promise is final
Reservation Named days, owner and expiry or release condition

Recheck the affected allocation if a condition changes before acceptance. Once the assignment is agreed, pass the same record to the delivery lead so the commercial promise and delivery schedule refer to the same work.

Keep the sales decision connected to the delivery plan

A CRM opportunity can hold the commercial context while a separate planning sheet contains the detailed allocations. Use whichever arrangement your team can maintain and find reliably. Someone reading the opportunity should be able to locate the current capacity decision and see who can confirm it.

When evaluating Konekt CRM, use this example to ask how your team would keep that decision and its supporting document together. Verify the configuration, access and plan needed for your intended setup. If resource scheduling is a buying requirement, ask for a demonstration of that task in the intended plan.

Before choosing a system, ask a colleague to find the promised start date, its conditions and the allocation owner without help from the proposal author. The buying decision should reflect whether the arrangement supports that real task.